@@ -58,6 +58,71 @@ This section outlines the planned release schedule and key milestones for the FO
+### Estimated Timeline for v1.2
+This table displays key milestones and dates related to the development of FOCUS Release v1.2 Specifications.
+
+
+ Date |
+ Milestone |
+ Comment |
+
+
+ 8-Oct-24 |
+ Start Work Item Preparation |
+ For Release v1.2, the group will implement a new process for creating Work Items. |
+
+
+ 8-Oct-24 to 21-Nov-24 |
+ Work Item Creation |
+ Six weeks (6) to develop the FOCUS Release (Rel) v1.2 scope. |
+
+
+ 21-Nov-24 to 3-Apr-25 |
+ Development Phase |
+ Nineteen weeks (19) to develop FOCUS Rel v1.2 specifications. |
+
+
+ 23-Jan-25 to 6-Feb-25 |
+ Interim Consistency Review |
+ Two weeks (2) for the Interim Consistency Review of FOCUS Rel v1.2. |
+
+
+ 3-Apr-25 |
+ End Development Phase |
+ End of FOCUS Rel v1.2 development. |
+
+
+ 3-17-Apr-25 |
+ Consistency Review |
+ Two weeks (2) for the Final Consistency Review of FOCUS Rel v1.2. |
+
+
+ 17-24-Apr-25 |
+ Preparing baseline for IPR Review |
+ One week (1) of preparation to start the IPR Review. |
+
+
+ 24-April-25 to 24-May-25 |
+ Start / End IPR Review v1.2 |
+ During this 30-day period, members may exclude essential claims from their licensing commitments. Contact the FOCUS Executive Director. |
+
+
+ 29-May-25 |
+ WG Approval v1.2 |
+ FOCUS Release Candidate v1.2 approved by the FOCUS members. |
+
+
+ 29-May-25 |
+ SC Ratification v1.2 |
+ FOCUS Steering Committee ratifies Rel v1.2. |
+
+
+ 3-Jun-25 |
+ FinOpsX Announcement |
+ FOCUS Rel v1.2 must be ready for announcement sometime in June. |
+
+
+
### Estimated Timeline for v1.1
This table displays key milestones and dates related to the development of FOCUS Release v1.1.