Story summary | Community material |
Iteration | ItEr70week06To07 |
FEA | ItEr70S03CommunityMaterialItEr69S03 |
Story Lead | |
Next Story | |
Passed acceptance test | No |
Acceptance Criteria
Additional Specification Comments
Implementation Notes
Delay Causes
Final or Pending Considerations
%RPSHOWGITCOMMITS%
Tasks | Est | Spent | To do | Risk | Reviewer | Developer | Task Name | Start Date | Est End Date | End Date |
---|---|---|---|---|---|---|---|---|---|---|
Task | 20 | 22 | 0 | Low | JavierMoran | ManuelRego | Web project management | |||
Task | 0 | 0 | 0 | Low | JavierMoran | JavierMoran | Web project management |
User | Spent in XpTracker | Spent in phpReport | Ok? |
---|---|---|---|
ManuelRego | 22 | 0 | |
JavierMoran | 0 | 0 | |
Total | 22 | 0 |