TWiki> LibrePlan Web>ItEr72week10To11 (20 Aug 2012, ManuelRego)EditAttach

Summary Iteration 72
Team LibrePlanTeam
Start 07/03/2011
End 20/03/2011

Iteration Details >>

Iteration summary

Story FEA Estimate Spent PhpReport ToDo Progress Done Overrun Completion Developer Reviewer
ItEr72S01Coordination
Coordination
ItEr72S01Coordination 4 2 0 0
smile
100% -50% Acceptance JavierMoran JavierMoran
ItEr72S02Analysis
Analysis
ItEr72S02Analysis 0 0 0 0
smile
100% 0% Acceptance JavierMoran JavierMoran
ItEr72S03CommunityMaterialItEr71S03
Community management
ItEr72S03CommunityMaterialItEr71S03 6.75 8.5 0 0
smile
100% +25% Acceptance ManuelRego JavierMoran LorenzoTilve JavierMoran LorenzoTilve
ItEr72S04BugFixing
Bug fixing
ItEr72S04BugFixing 105 140.25 0 0
smile
100% +33% Acceptance ManuelRego SusanaMontes JavierMoran LorenzoTilve DiegoPino JavierMoran
ItEr72S05PrintingSupportItEr70S06
Printing support
ItEr72S05PrintingSupportItEr70S06 40 2.5 0 0
smile
100% -93% Acceptance ManuelRego LorenzoTilve JavierMoran
ItEr72S06CalendarAdminInterfaceItEr70S07
Calendar administration interface refactoring
ItEr72S06CalendarAdminInterfaceItEr70S07 7.5 0 0 0
smile
100% -100% Acceptance LorenzoTilve JavierMoran
ItEr72S07AllocationStartEndAssistance
Planned workable days allocation calculation assistance
ItEr72S07AllocationStartEndAssistance 0 0 0 0
smile
100% 0% Acceptance SusanaMontes JavierMoran
Team totals   163.25 153.25 0 0
smile
100% -6%      

Developer velocity for iteration ItEr72week10To11

Who Assigned Spent PhpReport Remaining Completition   Assigned Tasks Remaining Tasks
LorenzoTilve 44.25 27.5 0 100%   4 0
ManuelRego 40 40.75 0 100%   3 0
DiegoPino 30 16 0 100%   1 0
SusanaMontes 30 60 0 100%   2 0
JavierMoran 19 9 0 100%   4 0