Skip to content

ItEr75S30SubcontractorIncommingCommunicationsLists

Jeroen Baten edited this page Mar 9, 2018 · 1 revision

TWiki> LibrePlan Web>ItEr75S30SubcontractorIncommingCommunicationsLists (03 Jan 2012, JavierMoran)EditAttach

Story summary Subcontractor incoming communication list
Iteration ItEr75week25To52
FEA ItEr75S30SubcontractorIncommingCommunicationsLists
Story Lead  
Next Story  
Passed acceptance test No

Acceptance Criteria

Additional Specification Comments

Implementation Notes

I had problems with some test, and with the entrypoints. Also when I used the new entrypoint to show the progress window, this one crashed and I took quite time solve the problem. The problem was the window was as modal but the mode is not established to modal.

solution : this.window.setMode("modal");

-- SusanaMontes - 15 Nov 2011

 

Delay Causes

Final or Pending Considerations

 

Commits

%RPSHOWGITCOMMITS%

Tasks in this story

Tasks Est Spent To do Risk Reviewer Developer Task Name Start Date Est End Date End Date
Task 10 10 0 Low JavierMoran SusanaMontes Create a list with all the communications received from subcontractors      
Task 5 7 0 Low JavierMoran SusanaMontes Check the incoming communications items coming from subcontractor companies as reviewed      
Task 3 17 0 Low JavierMoran SusanaMontes Include a filter in the subcontractor incoming communication list     0

Total Hours in this Story

User Spent in XpTracker Spent in phpReport Ok?
SusanaMontes 34 0 ALERT!
Total 34 0 ALERT!