Story summary | Community tasks |
Iteration | ItEr76Week01To33 |
FEA | ItEr76S03Community |
Story Lead | |
Next Story | |
Passed acceptance test | No |
Acceptance Criteria
Additional Specification Comments
Implementation Notes
Delay Causes
Final or Pending Considerations
-- ManuelRego - 22 Feb 2012
%RPSHOWGITCOMMITS%
Tasks | Est | Spent | To do | Risk | Reviewer | Developer | Task Name | Start Date | Est End Date | End Date |
---|---|---|---|---|---|---|---|---|---|---|
Task | 80 | 207.5 | 0 | Low | JavierMoran | ManuelRego | Community tasks | |||
Task | 40 | 45 | 0 | Low | JavierMoran | JavierMoran | Community tasks |
User | Spent in XpTracker | Spent in phpReport | Ok? |
---|---|---|---|
ManuelRego | 207.5 | 0 | |
JavierMoran | 45 | 0 | |
Total | 252.5 | 0 |