I am facing the problem that Countdown shows me 15 hours left until the end of the sprint. But the right number is 7. Today is the last day of the sprint and we only work 8 hours a day.
Maybe this is problem in azure devops. I could't find a way to configure our working hours. I can only configure the working days.
The text was updated successfully, but these errors were encountered:
3imuhanerd
changed the title
Countdown doesn't seem to take "Capacity per Day" into account, does it?
How to configure Countdown working hours?
Jan 24, 2020
The Countdown Widget counts down towards the end of the sprint, configured as days. It does not take into account the amount of working hours on a day, nor the business hours. Any implementation of this might not be as easy as it seems due to timezones and remote workers.
However, I would gladly accept a good PR that addresses this.
I am facing the problem that Countdown shows me 15 hours left until the end of the sprint. But the right number is 7. Today is the last day of the sprint and we only work 8 hours a day.
Maybe this is problem in azure devops. I could't find a way to configure our working hours. I can only configure the working days.