SRS: List of Groups

The following information pertains to the group responsible for implementing the IEEE Software Requirements Specifications documentation. This group is tasked with creating a document that outlines the functional and non-functional requirements of the software system. They are responsible for gathering the necessary requirements, designing the system, implementing and testing the software, and documenting the software development process. Effective communication, collaboration, and coordination between the group members are critical to ensuring that the project meets its objectives and is delivered on time and within budget. The group should adhere to the guidelines outlined by the IEEE for Software Requirements Specifications documentation and use clear and concise language, appropriate notation, and a structured format to ensure that the document is easily understood by all stakeholders involved in the software development process.

Sample SRS

No Title Document
1 MengajiOnetoOne Salary Management System
2 Vending Machine Inventory Management System

Section 1

No Topic Description Activity Document
1 Curiousity KTDI Events Management System
2 Lastminpotential Faculty of Computing Feedback System
3 Limapuluh UTM Student Feedback System
4 Cutie UTM Student Attendance Management System
5 Systema UTM Faculty of Computing Student Engagement System
6 Stakeholder Student Accomodation System in KTDI

Section 2

No Topic Description Activity Document
1 Allen KTDI Mini Mart Online System
2 Alpha College Room Rental System
3 Beta Food Ordering System at Arked Angkasa, UTM
4 Engineering Parcel Delivery Service
5 Program Academic Consultation System
6 Software Student Health and Wellness Management System
7 Tempest Badal Hajj and Umrah Management System

Gantt Chart for University Academic Course Registration System

Task Start Date End Date Duration
Requirements Gathering 10/01/2023 10/15/2023 10 days
Requirements Analysis 10/16/2023 10/31/2023 10 days
System Design 11/01/2023 11/30/2023 20 days
Frontend Development 12/01/2023 12/31/2023 25 days
Backend Development 01/01/2024 01/31/2024 30 days
Integration Testing 02/01/2024 02/15/2024 10 days
User Acceptance Testing 02/16/2024 03/01/2024 10 days
Deployment 03/02/2024 03/15/2024 5 days
User Training 03/16/2024 03/31/2024 10 days
Project Review 04/01/2024 04/15/2024 10 days

In this example, the Gantt chart breaks down the project into ten tasks, each with a specific start and end date, as well as a duration. The tasks include requirements gathering, analysis, system design, frontend and backend development, integration and user acceptance testing, deployment, user training, and project review.

Requirements Gathering Timeline

Task Start Date End Date Duration
Identify Stakeholders 10/01/2023 10/03/2023 3 days
Schedule and Conduct Interviews 10/04/2023 10/10/2023 5 days
Schedule and Conduct Focus Groups 10/11/2023 10/15/2023 5 days
Analyze Data and Identify Requirements 10/16/2023 10/20/2023 5 days

Requirements Analysis Timeline

Task Start Date End Date Duration
Review and Validate Requirements 10/21/2023 10/25/2023 5 days
Identify Conflicts or Inconsistencies in Requirements 10/26/2023 10/28/2023 3 days
Prioritize Requirements 10/29/2023 10/31/2023 3 days

In this example, the Requirements Gathering phase is broken down into four tasks, including identifying stakeholders, conducting interviews and focus groups, and analyzing data to identify requirements. This phase is expected to take 18 days in total, starting from October 1, 2023, and ending on October 20, 2023.

The Requirements Analysis phase, on the other hand, is broken down into three tasks, including reviewing and validating requirements, identifying conflicts or inconsistencies, and prioritizing requirements. This phase is expected to take 11 days in total, starting from October 21, 2023, and ending on October 31, 2023.