Skip to content
New issue

Have a question about this project? Sign up for a free GitHub account to open an issue and contact its maintainers and the community.

By clicking “Sign up for GitHub”, you agree to our terms of service and privacy statement. We’ll occasionally send you account related emails.

Already on GitHub? Sign in to your account

5.0.0-M5 Milestone Plan #2359

Closed
56 tasks done
bmicklea opened this issue Sep 6, 2016 · 0 comments
Closed
56 tasks done

5.0.0-M5 Milestone Plan #2359

bmicklea opened this issue Sep 6, 2016 · 0 comments
Labels
kind/planning A checklist of issues for planning a particular sprint.
Milestone

Comments

@bmicklea
Copy link

bmicklea commented Sep 6, 2016

Milestone Overview

  • Node.js debugging with GDB
  • Improvments to stack editing
  • PHP project type improvements
  • Bug fixes

Upgrade and Migration

This is a pre-GA milestone in the new Che 5 stream.

Due to a fundamental model change that allows us to deliver multi-machine support, it will only be possible to migrate 4.7.1 workspaces to 5.0.0 at GA (users who wish to try 5.0.0 milestone releases today will have to create new workspaces).

Docker Image Tags
While 5.0 is pre-GA the :latest tags on our Docker images will continue to point to 4.7.1. We will also create a new 5.0.0-latest tag to make it easier to try each 5.0.0 milestone release.

For more information about our development process please see our development process page.

Schedule

This release will be an Eclipse-signed and marketed release.

  • Code complete milestone: TBD
  • GitHub release complete (QA verified) milestone: TBD

Schedule Detail

Code complete milestone

  • Milestone issues complete
  • Smoke tests started

Release candidate created milestone

  • Release candidate created
  • Test cycles started
  • Docs complete

GitHub release complete (QA verified) milestone

  • Release completed and QA verified
  • Release notes updated
  • Final release information updated on GitHub
  • Docs reviewed and live

Target Milestone Issues

Epics and Issues

Bugs

@bmicklea bmicklea added the kind/planning A checklist of issues for planning a particular sprint. label Sep 6, 2016
@bmicklea bmicklea added this to the 5.0.0-M2 milestone Sep 6, 2016
@riuvshin riuvshin modified the milestones: 5.0.0-M3, 5.0.0-M2 Sep 20, 2016
@riuvshin riuvshin changed the title 5.0.0-M2 Milestone Plan 5.0.0-M3 Milestone Plan Sep 20, 2016
@riuvshin riuvshin modified the milestones: 5.0.0-M4, 5.0.0-M3 Sep 27, 2016
@riuvshin riuvshin changed the title 5.0.0-M3 Milestone Plan 5.0.0-M4 Milestone Plan Sep 27, 2016
@bmicklea bmicklea changed the title 5.0.0-M4 Milestone Plan 5.0.0-M5 Milestone Plan Sep 27, 2016
@bmicklea bmicklea modified the milestones: 5.0.0-M5, 5.0.0-M4 Sep 27, 2016
@bmicklea bmicklea closed this as completed Oct 8, 2016
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
kind/planning A checklist of issues for planning a particular sprint.
Projects
None yet
Development

No branches or pull requests

2 participants