Statistic of time-used vs. time-budget #416
Comments
Are you sure you are talking about Kimai 2? There is nothing like budget for now. |
@yweidmann I need further input, otherwise I can't help. |
Oups, sorry for keeping you waiting. From my point of view, an indication of how many hours are left for the individual activities would be great. I aggree that the rate is an important factor. But for discussions and group meetings, the number of hours will be more intuitive. |
Do you want to have budget on projects or activities or both? Edit: or are you still using v1 and this post is completely about it? |
No, it is all about v2.
Good question about the global activities.
|
Ok. I would have expected a budget rather on a project than an activity - so many things are handled different between companies, that its hard to find a way working for all. More question that come to my mind:
|
activity and project budgets influence each other or work completely independent:
should the budget be based on money or hours:
|
Can only agree!
|
Hi Kevin, we are using KIMAI V1 and also the Budget Control. In general we defined the budget on the Project level. In the End we like to have the same or similar functionality as in V1. Regards, |
Yes
I have my own ideas and already received some input, but if you have more ideas: please share them! |
So I added the budget field import from v1 to v2 and it works. We happen to use the budget field as hours budgeted per project. So when combined with the fixedRate for each project, Kimai should then be able to calculate the overall cost per project in terms of both budget dollars and expended dollars (via expended time obviously). I can give more information if needed, I hope this helps out. One other related area I noticed in the invoice area is that when you are making an invoice template, I can't see any option for "Project Grouped - One entry per Project". That would also be helpful for multiple projects per customer in the billing period. |
@ClintfromCanada new issues please And to all who commented. You have to vote in the inital posting via the 👍 reaction. |
Sorry - new to commenting in Github... I don't follow - did you want me to add the "One Entry Per Project" request as a new issue? |
Yes, exactly that - probably with some additional words about invoice etc. |
This thread has been automatically locked since there has not been any recent activity after it was closed. Please open a new issue for related bugs. If you use Kimai on a daily basis, please consider donating to support further development of Kimai. |
Dear Kimai
The budget always takes time * rate as reference. Is there a way to use only time (hours) as budget and showing the time (hours) available for each activity?
Thank you very much for any hints.
Best regards,
Yvo