Gantt excludes
breaking dynamic task duration
#5867
Labels
Status: Triage
Needs to be verified, categorized, etc
Type: Bug / Error
Something isn't working or is incorrect
Description
When an excludes day occurs within a task that doesn't have a fixed duration (uses
until
or fixed end), the duration of the task is extended.Steps to reproduce
e.g. task Two is supposed to occur until task three, but they overlap with the excludes day added
Screenshots
Code Sample
Setup
Suggested Solutions
No response
Additional Context
Note: This does not occur if the excludes day starts at the beginning of a task