Resource Profile Improvements
Michael Iatauro edited this page Oct 18, 2014
·
1 revision
Results of 9/10/08 discussion with Javier, Matt, Peng, Mike and Tristan.
We currently have two extremes:
- !TimetableProfile does fast/simple calculations. The regular flaw/violation detector will always report flaws with the resulting profiles, and the Timetable flaw/violation detector can be used to only report violations (ignore flaws)
- !FlowProfile (and !IncrementalFlowProfile, which does the same thing, just a bit more efficiently) does the best possible calculations based on the avialable constraints (TODO: what does 'best possible' really mean).
Note that in general flaws occur when LB < 0 and violations when UB < 0 (for the level can't be below 0 case, at least).
Possibilities, in a rough priority order:
- (general case) Tighten up Timetable profile. Take care of the obvious places in where flaws needn't exist (precedence chains, for example).
- Can we reduce the set of profiles computed from 4 down to 2 or 1 in various situations:
- (special case) If no variable production, we only need 2 of the profiles (upper upper, and lower lower)
- (special case) Can we reduce from 4 to 2 if we make standard assumptions about instantaneous or cumulative production/consumption.
- (special case) If Timetable profile is used with Timetable flaw/violation detection, can we just use a single profile (ie the one used for violations, not flaws)? Does this only work if we make assumptions about variable production/consumption and/or non-existence of instantaneous and/or cumulative limits.
- (special case) If we only have production, or only have consumption, do we need less information/computation?
- (special case) Special case unary resources. There should be a way to make this as fast as timelines, I suspect.
- (special case) Javier mentioned there may be additional insight in the Reusable case, where you know that every consumption will be followed by an equal production, and vice-vers#
- (special case) Grounded plans:
- I originally thought grounding meant that we would either:
- Only report violations after everything is grounded (easy, but too late?). It appears that using Timetable profile AND flaw/violation detector gets similar results, but is better, because not everything needs to be grounded.
- To calculate flaws/violations, create a profile by stepping through time and greedily choosing a time for each transaction (subject to all constraints), and reporting whether or not there is a violation, or something...
- Javier's notion of grounding, as I understand it, means that your plan is grounded, but you use information from that for no-good detection to figure out how to handle violations that do appear. Edge-finding algorithms may help here.
- (general case) Will edge-finding algorithms help in other cases?