Named budgets

Sharing budget between different use cases or different products can pose a challenge. If one of the use cases/products uses the contribution budget more quickly, it may exhaust the budget, preventing the others from being able to report. (For example, see issue #145.)

We propose a generic mechanism to better support this. Each reporting site would be able to define a series of named budgets and would allocate a fraction of their total budget to each, e.g.:

privateAggregation.reserveBudget("example-budget", 0.5);
privateAggregation.reserveBudget("debug", 0.125);

Then, when making histogram contributions (including via contributeToHistogramOnEvent()), a named budget can optionally be specified, e.g.:

privateAggregation.contributeToHistogram({
  bucket: 123n,
  value: 45,
  filteringId: 6n,
  namedBudget: "example-budget"
});

When approving or rejecting contributions, the browser would then check both whether the chosen named budget has enough allocated budget left and whether there is enough overall budget left. This ensures the overall budget is always respected, even if the named budget allocations change.

Fractional budget

We propose using a fraction to represent the budget allocation, i.e. not a direct limit on the contributions’ values sum. Given the two separate time windows used in Private Aggregation budgeting (per-10 min and per-day), using a fraction more clearly allocates a portion of both limits simultaneously.

Reservation persistence

To avoid the complexity of persisting configurations over time, we propose that the reserveBudget() calls are scoped to just the single worklet/script runner context. That is, the budget allocations would need to be set up at the start of each Shared Storage operation or Protected Audience function call. Note that the browser would still keep track of the budget usage for each group over the last 10 min and last 24 hours, but the per-named budget limits themselves would not be persisted.

See Future iteration: global config below for some discussion of a more persistent choice.

Default (null) budget

If no named budget is explicitly specified for a contribution, it would default to using a special “null” budget. This “null” budget is implicitly allocated the remaining budget after all the explicit reservations are accounted for. In the example above, the “null” budget would be allocated the remaining 37.5% of the budget. Note that this behavior means that this feature is fully backwards compatible.

Allocating more than the entire budget

If more than 100% of the budget is allocated to different named budgets, a JavaScript error will be thrown.

Privacy considerations

This feature also does not introduce any concerns as the overall existing budget is still always enforced. Note that contribution budgets are enforced per reporting site and so one reporting origin on a site could exhaust the budget for its entire reporting site. However, this is intended and is unchanged by the new feature.

Future iteration: global config

As a future extension, we could consider allowing these budget reservations to be set up globally for a reporting origin (or site). A global config has already been proposed for other use cases (see issues #81 and #143) so we could potentially use a single config for these use cases. This would reduce verbosity as reservations that don’t need to change frequently could be replaced. We may need to consider a mechanism that allows for canceling or overriding these globally configured details.