DevTeam Gantt Planner

DevTeam Gantt Planner is a Python-based tool designed to assist development teams in creating and visualizing Gantt charts for project planning and task management.

Features

Project Scheduling: Define features, define the required effort, assign them to developers within the DevTeam. Outline project timelines.

Team Assignment: Allocate tasks to specific developers or teams.

Gantt Chart Generation: Visualize project schedules through interactive Gantt charts.

Once a project is defined, it is possible to visualise it as Gantt chart with different levels of granularity (Project, Version). See below the Gantt chart for a specific version of the project :

image

At the developer level, the associated workload can be visualised under the form of a Gannt diagram, or a loadchart. Peaks overcoming 100% effort are highlighted in red :

image

image

Installation

Ensure you have Python 3.6 or higher installed. Then, install the required dependencies:

  pip install -r requirements.txt

Usage

Clone the Repository:

https://github.com/Iconeus/chargedPlanner

Prepare Your Data:

Create a json file named tasks.csv with the following structure:

{
    "devs": [
        {
            "devType": "Manager",
            "name": "<managerName>"
        },
        {
            "devType": "Dev",
            "name": "<devName>"
        },
}

Fill all the devs of your group and place the file in the project resource folder :

C:\Users\<currentUser>\.config\chargedPlanner\devs.json

Getting started :

from chargedPlanner import * 

charles = DevGroup()["Charles"]
selene = DevGroup()["Selene"]

connFeat = Feature(featName="Connectivity",
                   remainingEffort=5,
                   assignee=charles,
                   percentageLoad = 20,
                   startDate=datetime(2024, 12, 26).date())

seedMapFeat = Feature(featName="SeedMap",
                      remainingEffort=15,
                      assignee=selene,
                      percentageLoad=20,
                      startDate=datetime(2024, 11, 15).date())

scanV2Feat = Feature(featName="ScanV2",
                    remainingEffort=15,
                     assignee=charles,
                     percentageLoad=40,
                     startDate=charles.getEndDateForLatestAssignedFeat())

version1 = IcoStudioVersion("1.0.0")
version1.addFeat(connFeat)
version1.addFeat(seedMapFeat)

version2 = IcoStudioVersion("1.1.0")
version2.addFeat(scanV2Feat)

icoStudioProject = Project(IconeusProduct.IcoStudio)
icoStudioProject.addVersion(version1)
icoStudioProject.addVersion(version2)

print(icoStudioProject)
icoStudioProject.gantt()

version1.gantt()

charles.gantt()
charles.loadChart()

selene.gantt()
selene.loadChart()

icoStudioProject.serialise()

See the auto tests for code usage

Dependencies

See file : requirements.txt

Contributing

Contributions are welcome! Please fork the repository and submit a pull request with your enhancements.

License

This project is licensed under the MIT License. See the LICENSE file for details.

Acknowledgments

Special thanks to the contributors of the following resources: Gantt Charts in Python - Plotly

About

DevTeam Gantt Planner is a Python-based tool designed to assist development teams in creating and visualizing Gantt charts for project planning and task management.