This is a tentative schedule for the stabilization and rollout of v1.17. It is for informational purposes only and all dates are subject to change. Please wait for announcements on Discord before performing any upgrades or downgrades.
Week # | Monday Date | Goals |
---|---|---|
1 | 2023-10-02 | Create v1.17 branch. Testnet: Upgrade to v1.17.0. |
2 | 2023-10-09 | |
3 | 2023-10-16 | Last week for backporting changes that aren't bug fixes. |
4 | 2023-10-23 | |
5 | 2023-10-30 | Breakpoint Publish v1.17 audits. |
6 | 2023-11-06 | Devnet: Upgrade to v1.17. |
7 | 2023-11-13 | |
8 | 2023-11-20 | US Thanksgiving. Tag Mainnet-beta Upgrade Candidate (MUC) on v1.17 branch. |
9 | 2023-11-27 | Testnet: Restart on v1.16 with v1.17 feature gates deactivated. Testnet: Upgrade to MUC (gradually: 10%, 25%, 100%) |
10 | 2023-12-04 | Testnet: Live downgrade to v1.16, upgrade to MUC (100%), feature gates re-enabled (all at once) Mainnet-beta: Ask for volunteers to take 10% of stake to to v1.17 |
11 | 2023-12-11 | |
12 | 2023-12-18 | Mainnet-beta: Ask for volunteers to take 25% of stake to to v1.17 |
13 | 2023-12-25 | Christmas |
14 | 2024-01-01 | Testnet: Downgrade to v1.16, upgrade to v1.17 Mainnet-beta: Recommend all nodes upgrade to v1.17 |
15 | 2024-01-08 | Testnet: Upgrade to v1.17.15. Downgrade to v1.16.26. Upgrade to v1.17.15 and resume feature gate activations Mainnet-beta: Ask for volunteers to take 25% of stake to to v1.17 |
16 | 2024-01-15 | Mainnet-beta: Recommend all nodes upgrade to v1.17 |
17 | 2024-01-22 | Branch v1.18 off master, tag v1.18.0, and ask testnet to upgrade to v1.18.0 once a supermajority of mainnet-beta stake has upgraded to v1.17 |
18 | 2024-01-29 | Mainnet-beta: Begin activation of v1.17 feature gates |