How do I configure it so it will create 5 plots in parallel at the exact same time, and then once those plots are complete do 5 plots in parallel again and so on without specifying any specific times.

Generally it is not advisable to start plots at the exact same time, so set a global stagger of 5 minues, then 5 plots will start over a period of 5 minutes

Also is plotman aware of plots being done by the Chia GUI?

It should be, but there were some bugs which should be resolved in latest release