Notifications
You must be signed in to change notification settings - Fork 81
Timeline milestones schedule
vanevery edited this page Jan 13, 2011
·
9 revisions
First phase of this project is 3 months: January 1 to April 1 2011 We'll have weekly meetings/working sessions each Tuesday. Each month will have a major development milestone which will be broken down into a week by week schedule.
Phase/Month 1:
- Proof of concept app using (only) Android SDK - Camera/Gallery, Auto Face Blur, Manual Blur, Save and Share Functionality
- Investigation, choosing and compilation of native libraries (OpenCV, etc.)
- Research what is out there, documentation, outreach
Phase/Month 2:
- Alpha app development using choosen native libraries
Phase/Month 3:
- Testing, Revisions, Video, Beta
Outline of expected milestones for each week.
Jan 4: Project Kickoff/Team Meeting/Organization
- Setup Source Code Repository, Mailing List, Wiki
- Determine and Document Project Requirements and Schedule
- Write up User Scenarios
- Define Project Roles and Recruit Help
- Determine Related or Useful Projects or People and Make Contact
- Setup of GIT Project for Phase 1
- Start investigation of various native libraries
Jan 11:
- Start on Phase 1: UX/Design, Proof of concept development
- Put on a public face - Start outreach to other interested parties
Jan 18:
- Proof of concept complete
Jan 25: