Casino Royale

Deviations from Work Distribution and timelime

We've been able to maintain mostly the same timeline and work distribution from our original plan, however we only
have the one Pi, so more of the hardware work has fallen on Niko since he has the device. The other part of our plan
that we need to figure out is the setup of the Pi for the final demo. Initially we were thinking about having a plexiglass
table that the Pi could look up through to scan the cards, but we may have to change this.

We should also be able to maintain the same timeline from our original plan.

Where we fell behind

We haven't been able to work on setting up the Pi so that it's not handheld. Ideally we'd build a table with a
clear top so that the Pi could scan all of the cards from below, but we'll have to discuss this further since we
would have to meet in person to have the Pi and table together.

How we plan to catch up

We've been able to communicate pretty effectively using groupme and text, so integrating all of the parts of the project
shouldn't be too difficult. If possible Niko and I could meet up to integrate the Pi itself with the table.