Team 24 - Successorator


Milestone 1 Velocity Calculations

Iteration 1

  • Initial velocity estimation: 0.5

Iteration 2

  • Factors taken into consideration:
    • All group members with major time conflicts preventing many in person meetings
    • Heavy coursework loads
    • Midterm fiasco siphoning time to work on Successorator
    • Relative lightening of work and exams of all group members in iteration 2
  • Conclusions:
    • Majority of work for iteration 1 must be pushed to iteration 2
    • Increase work days from 5 to 7 days a week
    • Decrease velocity to 0.4
  • Iteration 2 work hours: 674 = 168 potential work hours -> 0.4*168 = 67.2 total work hours

Milestone 2 Velocity Calculations

Iteration 1

  • Factors taken into consideration:
    • Availibility of all group members for iteration 1
    • Performance of team during iteration 2 of Milestone 1
    • Difficulty of the tasks for iteration 1
  • Conclusions:
    • Maintain velocity of 0.4, carried over from iteration 2 of MS1
  • Iteration 1 work hours: 654 = 120 potential work hours -> 0.4*120 = 48 total work hours

Iteration 2

  • Factors taken into consideration:
    • All group members with major time conflicts preventing many in person meetings
    • Heavy coursework loads
    • Amount of work left in entire project
    • Certain tasks led to many unexpected problems, leading the task to take much longer than the initial estimation
  • Conclusions:
    • Roll over any tasks that were unfinished in iteration 1 to iteration 2
    • Maintain the 7 days per week of work, as most member had time during the weekends
    • Increase hours per day from 4 to 5 hours
    • Decrease velocity to 0.3
  • Iteration 2 work hours: 675 = 210 potential work hours -> 210*0.3 = 63 total work hours