The request date is modified when an action is done on the loan #2235
Labels
bug
Breaks something but is not blocking
f: circulation
Concerns the circulation interface or backend
p-High
High priority (to be solved in the 2-3 next months)
production
Issue specifically spotted on the production server
Describe the bug
The date of the request is modified to the checkin date of the requested item. The request queue seems then to be wrongly ordered, but in fact the request date is wrong.
To Reproduce
[to be completed, reproduced]
Expected behavior
The request date should always be the request creation date.
Context
v1.4.5