Tentative schedule, actual dates/times TBD.
5 meetings between steering committee and writing team. There are two milestones at 40% and 60% of the project, so these meetings mark the start, mid-point and end of each phase.
Writing team to meet regularly in between to check progress
- Kickoff Phase 1, May 16
- progress sync 1, May 30
- progress sync 2, June 13
- Mid-Phase 1, June 27 2022
- progress sync 3, July 13
- Delivery Phase 1 + Kickoff Phase 2, July 29
- progress sync 4, August 15
- progress sync 5, August 29
- progress sync 6, September 12
- Mid-Phase 2, September 26
- progress sync 7, October 10
- progress sync 8, October 24
- progress sync 9, November 7
- Delivery Phase 2, November 15
November 15 - November 30: organization administrators prepare and submit case study.