Sprint Planning
Kathryn Baker edited this page May 3, 2024
·
21 revisions
Sprint planning is the meeting where we decide what will appear in next sprint. We assign these roughly to high/medium/low priority tickets, and give them a points
value to indicate a rough estimate of effort involved in those items. This is all done through the current Program Increment (PI) project on GitHub.
All team members should add the proposal label to tickets that should be considered whenever they are aware of this. These will automatically be added to the appropriate Program Increment project in GitHub. The project manager (or an agreed alternative team member) should do the following prior to the meeting, either late the day before, or the morning of the meeting:
- Ensure that all proposed items are in the appropriate
Sprint
, most easily done on thePI Summary
tab. - On the
Breakdown by Sprint
board, check the items in theNo Sprint
column to see if they should be assigned to the next sprint - these are in priority order for the PI. - Update the
Planning Board
andPlanning Table
tabs to filter on the Sprint to be planned. - Any items from the current sprint in the backlog, but without a rework label, are assigned to the Sprint to be planned.
- Create a support ticket based on the contents of the support channel (adding one tally for each thread, and for every multiple of 10 in the comments, so a thread with 23 comments would get 3 tally marks), and assign it to ISIS Builder with the appropriate number of points
- Remove the automation from the
Review Complete
column of the IBEX board, rename that column to be the name of the sprint ending - Create a new
Review Complete
column which is automated to theDone
type based on the closing of a ticket
- Post a link to the planning poker site and a reminder of the points estimates to the chat in zoom. This information is available in the
Planning
tab on the IBEX Developers MS Teamsannounce
channel. - For each ticket in proposed (this should be kept to a maximum of 5 minutes per ticket if possible):
- Read the ticket and understand the issue
- Make sure the acceptance criteria makes sense
- Select the priority of the ticket high/medium/low and move to that column
- If a ticket is to be delayed to a later sprint in this PI, change the assignment of the ticket
- If a ticket should be delayed to the next PI, assign it to the appropriate Sprint
- If a ticket is put on hold for longer than that, simply remove it from the PI project
- Estimate the ticket using planning poker site; there is no need if it is already pointed; Points should be provided as a label at the minimum during the meeting, the field in the project is not in use as of May 2024 when this was updated
- Remove any tickets in the
Ready
column of the IBEX project board that are not reworks - Add the tickets from the planning board in order from the top of High to the end of Low
- Set the milestones of tickets to the appropriate milestone (those in
Ready
,In Progress
,Impeded
,Review
, andReview Complete
should all have the current milestone) - this is most easily done at present through the issues list and filtering - Remove the proposal label from all tickets - this is most easily done at present through the issues list and filtering