Story summary Make the load chart as a grid
Iteration AnA08Usability
FEA AnA08S06GridLoadChart
Story Lead  
Next Story  
Passed acceptance test No

Tasks

Change the way it is represented the load chart

In this task it is wanted to change the way the data is represented in the load charts. The problem is that currently it is only showed one point per time unit. There are two time units:

  • One day time unit for the day zoom level. In this case, the time unit is the day and it is represented one point per day.
  • One week time unit for the week and zoom level for week and

The change will be to add to point per time perior to avoid the bad effects.

  • (init_time_interval , finish_time_interval-epsilum)
  • epsilum = minimum unit of the data type used in the load chart (for example, milliseconds).

User stories

Tasks Est Spent To do Risk Reviewer Developer Task Name Start Date Est End Date End Date
Task 7 7 0 Low JavierMoran SusanaMontes Change the way it is represented the load chart      

Total Hours in this Story

User Spent in XpTracker Spent in phpReport Ok?
SusanaMontes 7 0 ALERT!
Total 7 0 ALERT!