Tasks

Include specific allocation load to criterion load analysis

This task is related to the resource load view filtered by criteria. In this case, now it is not included in the computed allocated hours the load because of the specific resource allocation.

So, the changes to introduce are the following:

  • Add a last second level per criterion called "specific allocations". This second level wil be an aggregation of all the specific allocations of the resources fulfulling the criterion.
  • The third level will be composed of all the specific allocations of the resources satisfying the criterion represented by the first level.

The query to get the specific allocations of the resources satisfying the criterion should follow the following guidelines:

  • Get the time axis which is being displayed in the resource load screen.
  • Get the resources which satisfy the criterion in any of the points of the time axis.
  • Get the resource allocations of those resources in the time period of the time axis.
  • Check that each in any of the points of the specific resource allocation the resource satifies the resource.

warning About the guidelines, think of how to do the querys or these steps in the more effective way from performance point of view.

User stories

Tasks in this story

Tasks Est Spent To do Risk Reviewer Developer Task Name Start Date Est End Date End Date
Task 9.75 4.75 5 Low JavierMoran OscarGonzalez Include specific allocation load to criterion load analysis      