Summary Iteration 66
Team LibrePlanTeam
Start 20/12/2010
End 02/01/2011

Iteration Details >>

Iteration summary

Story FEA Estimate Spent PhpReport ToDo Progress Done Overrun Completion Developer Reviewer
ItEr66S01Coordination
Coordination
ItEr66S01Coordination 5 2.5 0 0
smile
100% -50% Acceptance JavierMoran JavierMoran
ItEr66S02Analysis
Analysis
ItEr66S02Analysis 0 0 0 0
smile
100% 0% Acceptance JavierMoran JavierMoran
ItEr66S03CommunityMaterialItEr65S04
Community material
ItEr66S03CommunityMaterialItEr65S04 23 30.5 0 0
smile
100% +32% Acceptance ManuelRego JavierMoran JavierMoran
ItEr66S04BugFixing
Bug fixing
ItEr66S04BugFixing 85 55.75 0 0
smile
100% -34% Acceptance ManuelRego OscarGonzalez SusanaMontes JavierMoran JavierMoran
Team totals   113 88.75 0 0
smile
100% -21%      

Developer velocity for iteration ItEr66week51To52

Who Assigned Spent PhpReport Remaining Completition   Assigned Tasks Remaining Tasks
ManuelRego 30 27.5 0 100%   3 0
SusanaMontes 30 15 0 100%   1 0
OscarGonzalez 30 33.25 0 100%   1 0
JavierMoran 23 13 0 100%   4 0