TWiki> LibrePlan Web>Meetings>MinuteS20120410 (25 Apr 2012, ManuelRego)EditAttach
- Date: April 10, 2012 at 16:30 CET (GMT +2)
- Agenda: Coordination meeting
- Log:
libreplan-coordination-meeting-20120410.txt
- Susana Montes
-
- Finishing the tasks ItEr76S21UpdateEndDateToCustomer
- Fixed bug #1234
-
- Work in the tasks defined at ItEr76S22ExpenseTrackingSystem
-
- Manuel Rego
-
- Finished task ItEr76S17MoneyCostMonitoringSystem (merged in both master and libreplan-1.2)
- Blog post about this feature: http://blogs.igalia.com/mrego/2012/03/28/money-cost-monitoring-system-in-libreplan/
- Fixed bugs #1403, #1406, #1298, #1349 and #1402
- Reviewed doc about JAVA_OPTS and add info in INSTALL file (related to bug #1404)
- Finished task ItEr76S14ConcurrencyProblemWorkReports. We don't have concurrency issues anymover between projects and work reports screens \o/
- Merged project-dashboards branch into master
- Remove CutyCaptTimeout as it was not been used since June 2011
-
- Update keys.pot files and notify the translators
- Test LibrePlan for release 1.2.3
- Try to find a solution for PostgreSQL procedure in version 8 from Debian package
- General bugfixing and patch review
- Carry on with binding user-resources task for LibrePlan 1.3
-
- Loren Tilve
-
- Fixed some small things on the website
- Managed collaboration of Mar Castro for Spanish translation of the website. She used some tool to generate
.po
files from the HTML. - Created a very initial draft for the improving of the help system
-
- Devote some time to KPIs branch
-
- Javi Morán
-
- Meeting with Javier Toja to guide him how to go on with the Mantis integration
- Did an analysis to program the first feature about this: ItEr76S20ConnectionConfiguration
- Analysed a new set of tasks about subcontractor module. User story: ItEr76S21UpdateEndDateToCustomer
- Working in the analysis of a part of LibrePlan audivisual that will be part of LibrePlan core. It is a expenses tracking system AnA19S02ExpenseTrackingSystem
- Coordination and community management (forums mainly)
-
- Keep with the expense tracking system and other audivisual analysis
- Do the user binding analysis
-
- Diego Pino
-
- Worked in optimization of second level cache and batch fetching
- Second level cache is enabled
- Batch-fetching was more difficult and it didn't totally work. There were some LazyExceptions while retrieving some entities
- For the moment using a new remote branch
cache-tunning
- Worked in optimization of second level cache and batch fetching
-
- Carry on with batch-fetching
- Test performance improvements with jmeter (more info at ItEr74S08DeployFramework and ItEr75S19DeployFrameworkItEr74S08)
-
- Nacho Díaz
-
- No time
-
- Send 2 patches with the fixes needed for some patches sent a few weeks ago
-
- Javi Toja
-
- Meeting with Javi Morán
- Started with configuration screen in ZK to connect with Mantis
- Completed the WS client to connect Mantis and LibrePlan
- Configured some Liquibase database changes
-
- Carry on with the configuration screen changes
-
- At the end we talked about LibrePlan 1.2.3. That will be released in week 16 with the following main changes:
- New feature: money cost bar
- New language: Polish
- As usual some bugfixing
- About the mobile application that was in the roadmap for 1.3. We discussed about the possible technology to do that application. The options were do an Android native application or use PhoneGap in order to create a multi-platform application. There were some doubts regarding storage in PhoneGap but they were solved, so finally we are going to use PhoneGap for the mobile application.
- LibrePlan 1.3 should have been released past week, so we're delayed. In the next coordination meeting we'll try to define a new date for the release.